Quality of services
Our specialized erectors start the erection in-accordance with the drawing issued for construction. The assembly and erection is done at braced bay between any two brace bay grids and braced bay will be assembled including all main frame items and the erection of the braced cables. Our team erect first column and guyed it off. After the first assembly of rafter through the cranes shall be controlled by guide ropes and carefully maneuvered into specified The basic requirements of building to be erected are; cleaned leveled and ready site for storage , maneuvered space for equipment and clear ground for moving scaffolding or scissor lift. Position by the synchronized movements of the crane booms. The crew will make the bolt connections and the knee bolts at the columns.